A-500 · Progress

Rising on Riverside.

The building goes up in public. This page follows the programme, from the first pile to the keys, and is brought up to date as each stage is reached.

Overall
24%
On site now
Frame at level 7
Completion
Dec 2028
As at
19 Oct 2026
The frame today: level 7GL02L04L06L08L10L12L14L16Today
A-501 South elevation. Storeys with their frame built are solid; the one under way is hatched.

The programme

  1. 21 Nov 2025

    Approvals granted (done)

    Planning and environmental approvals for seventeen storeys and 86 homes.

  2. 13 Jan 2026

    Site hoarded and cleared (done)

    The plot fenced, trees marked for keeping, and the old structures taken down.

  3. 10 Feb 2026

    Ground broken (done)

    Work starts on the foundations.

  4. Mar to May 2026

    Piling and the basement dig (done)

    Bored piles, then two basement levels dug for parking and plant.

  5. 16 Jun 2026

    Ground-floor slab poured (done)

    The basement is closed in and the frame can start to rise.

  6. Jun 2026 to Apr 2027

    The frame rises Under way

    A floor about every eighteen days: columns, then the slab above.

  7. Feb to Dec 2027

    Façade, bays and windows

    The bays go on from the bottom up, closing in each floor as the frame moves ahead.

  8. 21 Apr 2027

    Topping out

    The roof slab poured, seventeen storeys up.

  9. Jun 2027 to Oct 2028

    Services and fit-out

    Power, water and air, then kitchens, bathrooms, floors and joinery.

  10. 16 Sep 2027

    Show apartments open in the building

    Viewings move from the sales suite to finished homes on level 3.

  11. Aug to Nov 2028

    Lifts, pool and gardens

    Commissioning and testing, and the planting of the gardens.

  12. 16 Dec 2028

    Completion

    Handover of the first homes begins.

A-502 · From the site

Photographs, newest first.

  • The frame passing level six, with the deck for level seven being set.
    10 Oct 2026 The frame passing level six, with the deck for level seven being set.
  • The frame at level three, from the street.
    22 Aug 2026 The frame at level three, from the street.
  • The ground-floor slab, with the basement closed in below.
    27 Jun 2026 The ground-floor slab, with the basement closed in below.